2017年6月26日星期一

The basic operation points of concrete batch plant

As a batching plant manufacturer with more than 15 years experience ,tell you some basic operation points of concrete batch plant in actual operation.


First, the construction sites
Concrete batch plant construction site should be keep clean, drainage unblocked, the signal connection.
Second, the feeding system should prevent institutions aggregate into operation;General sand and cement cannot be the same pipe groove;Hopper, tube slot parts of materials such as each time should be discharged net, shall not be reserved for the next feeding.
Third, feeding material,You can use a feeding and multiple feeding, a feeding material is in accordance with a certain process sequence into the concrete mixer, but does not allow the first investment in cement, so as not to cement sticky axis; a feeding time in order to avoid the cement is wrapped with water to form cement balls, The cement and sand and gravel stir, so that after the cement dispersed, and then shower; repeated mixing of concrete, also known as shelling concrete, it is more complicated feeding operation, in the batch plant and concrete mixing plant in the need for special treatment can be achieved.
Four,the running,In the operation of the concrete mixing station to control the measuring accuracy, stirring time, ensure meet the process requirements;On the other hand also want to check the abnormal and failure, such as discharging mouth without leaking slurry, etc., if there is abnormal and failure to timely maintenance.
Five,closing down,Before the shutdown must be out of the net concrete; work after the completion of the shutdown, the application of a small amount of stone and water washing mixer; the same time, clean up the mixing site. When a sudden power failure or failure to stop, should be careful to operate in time to clean up the concrete inside the host out.
The resource is from:

没有评论:

发表评论